Category: Dining Room

Catching up

We’ve visited the house twice since the last post, in fact I’m writing this one having just spent the day working there, but you’ll hear about that in the next post. Today I’ll share the updates from our last visit.

DCIM100GOPRO

The framework making up the ‘landing’ has been completed and the remainder of the old gable has been removed. On the other side of the tarp is the beginnings of our balcony!

DCIM100GOPRO
The wall between the landing and the bathroom has been erected
DCIM100GOPRO
Now we can see the actual size of the bathroom

 

Not only have they finished the landing structure, but they’ve also got the bedroom up as well.

The next surprise was that the wall and door under the main staircase have gone, opening up the hallway space and making the room feel so much bigger! Eventually we’ll have a glass balustrade instead.

DCIM100GOPRO DCIM100GOPRO

Finally, we decided during our last visit that the empty doorway between the dining room and the sun-lounge wasn’t really how we wanted it to stay, so the pillars have now been removed leaving a much larger double-doorway.

DCIM100GOPRO

In the summer the sun-lounge becomes like an oven and the lack of door means that the heat is passed straight into the dining room and raises the temperature of the house considerably. So we’re going to have some doors added in to regulate this somewhat. We just need to decide if they’ll be sliding doors, bifolds, or just regular doors!

Advertisements

Doorways

After the small trickle of construction in the last post, it feels like the flood gates have opened. There has been some further progress in the kitchen which I’m sure is not as major as it feels, but it feels huge.

The door between the dining room and lounge has been blocked up and the party wall has been constructed between the kitchen and the WC – also forming the new kitchen doorway. Now we can really see the shape and size the kitchen will be.

DSC_0012 (Medium)DSC_0016 (Medium)

 

 

 

DSC_0013 (Medium)

The holes left by the chimney in the dining room ceiling and floor have also been covered over. Now we will find out if we have enough spare wooden bricks to complete the parquet floor.

DSC_0015 (Medium)

We’re off to Edinburgh this weekend for a friend’s wedding, so we’ll stop at the house for a couple of days on the way home next week and get to see the changes in person again.

Stairway to Heaven (well, the loft)

IMG-20170313-WA0000More photos have made their way to us and we were pleased to see that the loft ladder has now been installed in the ‘den’ which will become my office. Access to the storage space was previously via a small hatch in the upstairs bedroom. This will become our new bathroom and we didn’t want to waste the available space in there, so Sarah had the great idea of installing a loft hatch for access from below.

We have also heard that the scaffolding has gone up around the rear of the building now, so hopefully work on the upper part of the project will be able to commence shortly.

IMG-20170313-WA0002One change that caused great amusement to Stuart my father-in-law, was the addition of a wheelbarrow to the dining room.

We shall be heading up North ourselves at the beginning of April to attend a friend’s wedding, so we’ll be spending a few days at the house too and see the changes for ourselves.

 

More destruction

The destruction continues!

May dad sent me a message today asking if there was any more progress on the house. “Nope” I said, only to be proved wrong when Sarah got home and declared “The chimney’s gone!”.

It’s extremely exciting to see and hear about progress happening, but also really frustrating that we are so far away from it that we don’t really know exactly what’s going on and where it’s at.

Sarah’s mum sent us photos of the progress. The last portion of the chimney has now been removed meaning there is a hole all the way from the roof to the floor of the cellar.

IMG-20170306-WA0003
Dining room floor
IMG-20170306-WA0005
The cellar is slightly more roomy now!

 

 

 

 

 

 

 

 

 

 

 

 

 

 

As well as the de-struction there has actually been a little con-struction happening. A lintel has been installed in place of the arch that used to separate the toilet from the rest of the bathroom. A partition wall will be installed set forward from and overlapping part of the existing one to allow space for a small basin to be installed. They have also added the brickwork and lintel which complete the new doorway from the kitchen into the hall.

IMG-20170306-WA0002
Taking shape

We don’t know the order things will be done in at the moment, but I’m hoping that they’ll make good all the downstairs rooms before starting to work on the upper rooms and roof. That way we’d be able to think about some decorating during Easter or the May half-term. That would mean some rooms would be almost finished! Too much to hope for?